JNE Automation, together with Dofasco, provided site investigation
services and project definition services for the replacement of the
existing Level 1 Control Systems for the No. 2 Hot Strip Mill. The
existing systems were contributing to unscheduled stoppages and
required high levels of maintenance to keep the mill running.
The DCS and PLC control systems to be replaced were on the
Rougher Mill, the Down Coilers and the Reheat Furnaces. The existing
systems were a 1980’s vintage and spares were scarce and
expensive.
The goal of the project was to carry out a phased change-over of
the existing Level 1 control systems in a manner that would
minimize the risk to the mill operations and would be carried out
without unscheduled downtime.
JNE Automation was responsible for managing the process to
produce the definition and subsequent installation scope of work
and to manage installation estimates and construction engineering
estimates. The report involved field investigation of the existing
control systems and drives, development of a change-over plan,
preparation of a scope of work for the change-over and estimates
for construction engineering and Contractor cost budgets.
The report produced enabled Dofasco to prepare the Project
Authorization Request for funding.
Dofasco plans to implement the control system upgrades and
replacements in 2007/2008.
|